Update 3/16/2016 7:00pm.  The work has been completed and power has been restored.to all outlets. Please report any network issues to the ITS Help Desk at 740-587-6395 or helpdesk@denison.edu. The Help Desk will reply as soon as possible during regular business hours (see www.denison.edu/its/helpdesk for hours).

Update 3/16/2016 10:00am: The old UPS was taken down at about 9:00am.  It is currently being dismantled and removed from the building.

Update: We have been informed that the contractor expects to turn down the old UPS tomorrow morning, 3/16/2016, between 8 and 9am.  They expect it to be down until sometime in the afternoon.

Update: The contractor has informed us that they will begin work at 8am Tuesday, March 15th, but will not be affecting power until late Tuesday or Wednesday morning.

A new uninterruptible power supply (UPS) will be installed in Olin on March 15-16.  During this time the power to outlets in Olin that are currently connected to the UPS will be off. During the constructions, we will attempt to have the data network available on the Ground, 1st and 3rd floors of the building.  However, these areas will be susceptible to utility power outages during the construction.  After the new UPS has been installed, the outlets will be connected to the new unit as well as have generator power during extended power outages.