Completed: Planned Network Outages Wed 7/22- Fri 7/24 5-7am and Tues 7/28-Thurs 7/30 5-7am

Update 7/30/2015 7:15am: This planned outage is complete.  The network is up and stable.

Update 7/28/2015 7:15am: This morning’s work is complete. The network is up and stable.  Note that the Wednesday, 7/29 work has been postponed until Thursday, 7/30/2015 5-7am.  The buildings that will be affected include Fellows, Barney, Library, Ebaugh, Higley, Olin, Swasey, Talbot, Slayter, and Knapp.

Update 7/24/2015 12:30pm: The campuswide outage scheduled for 8/1/15 has been postponed to a later date. A new announcement will be posted once it has been rescheduled.

Update 7/24/2015 12:00pm: A problem with people connecting to the network on wired ports in the dorms was found.  The problem has been corrected.

Update 7/24/2015 8:40am: A problem with people logging into their systems in the administrative offices was reported.  The problem has been corrected.

Update 7/24/2015 7:00am: This mornings’ work is completed. The network is up and stable.

Update 7/22/2015 3:15pm: Thursday’s maintenance has been postponed to Friday 7/24 from 5-7am.

Update 7/22/2015: This mornings’ work is completed.  The network is up and stable.

Update 7/20/2015: The initial work to be done on Tuesday 7/21 has been postponed to Wednesday 7/22 from 5-7am.

Original Message:

ITS will be performing upgrades to the network infrastructure over the next 2 weeks. While the upgrades are happening there may be brief interruptions to on-campus services and to Internet traffic from on-campus. Accordingly, ITS recommends that you DO NOT edit files over the network or submit information online during the following time periods as your work may be lost when the network outages occur.

 

  • Tuesday 7/21-Friday 7/24, 5:00-7:00am
  • Tuesday 7/28-Thursday 7/30, 5:00-7:00am
  • Saturday, 8/1, 7:00-9:00am (POSTPONED to a later day)

 

This post will be updated as the work is completed on each date.