Updated configurations on most admin and academic building up-links between 6am – 7:30am this morning. Will finish the remaining academic and admin buildings after 4:30pm today (Bryant, Physical Plant, Sigma Chi, and Library). Will be updating configurations for dorm up-links throughout the day. We will post updates as we start and finish general areas of campus. The configuration changes may cause a momentary slowness or connection drop.
**Update** 1:21pm Starting config changes on South campus dorms.
**Update** 1:50pm Done with South campus dorms starting East campus dorms.
**Update** 2:10pm Done with East campus dorms starting with West and North campus dorms.
**Update** 3:00pm Done with West and North campus dorms.
**Update** Done